This project is defined as "Sale of water treatment system including Lamellard clarifier pre-treatment unit, UF and reverse osmosis (RO) desalination plant for water production with a capacity of 500 cubic meters per day" for the employer "Mallard Agro-Industrial Complex" and is classified as non-construction projects. The implementation of this project started on 27/07/1401 and according to the recorded information, it is in the completion status. The contract period has also been announced as 3 months and these records show that the project has progressed within the framework of a specific and documented technical and executive cooperation.